Section 8: Ramp Closures Planned at I-4/S.R. 417/S.R. 46

December 3, 2021

Nightly ramp closures are scheduled Sunday, Dec. 5, through Friday, Dec. 10, at State Road (S.R.) 417 and Interstate 4 (I-4). Multiple ramps will close for bridge work.

 

Please see the following closures and detours:

  • Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road
  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to westbound/eastbound I-4 and International Parkway (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Additional nightly ramp closures planned for Sunday, Dec. 5, through Monday, Dec. 6, are listed below:

  • Westbound I-4 ramp system to southbound S.R. 417 and C.R. 46A (8 p.m. – 6 a.m.): Use International Parkway to C.R. 46A
  • Eastbound and westbound S.R. 46 to westbound I-4 (8 p.m. – 6 a.m.): Use International Parkway

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 8: Ramp Closures Scheduled at I-4/S.R. 417

November 29, 2021

Nightly ramp closures are scheduled Monday, Nov. 29, through Friday, Dec. 3, at State Road (S.R.) 417 and Interstate 4 (I-4). Multiple ramps will close for bridge work.

 

Please see the following closures and detours:

  • Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road
  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to westbound/eastbound I-4 and International Parkway (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

Section 8: Ramp Closures Planned at I-4/S.R. 417

November 18, 2021

Nightly ramp closures are scheduled Sunday, Nov. 21, through Tuesday, Nov. 23, at State Road (S.R.) 417 and Interstate 4 (I-4). Multiple ramps will close for bridge work.

 

Please see the following closures and detours:

  • Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road
  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to westbound/eastbound I-4 and International Parkway (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 8: Ramp Closures Planned at I-4/S.R. 417/S.R. 46

November 12, 2021

Nightly ramp closures are scheduled Sunday, Nov. 14, through Friday, Nov. 19, at State Road (S.R.) 417 and Interstate 4 (I-4). Multiple ramps will close for bridge work.

 

Please see the following closures and detours:

  • Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road
  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to westbound/eastbound I-4 and International Parkway (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 6: Lane Closures and Traffic Pattern Changes Planned at S.R. 46/Wekiva River Road

November 8, 2021

Extended lane closures and road work are planned at Wekiva River Road and State Road (S.R.) 46 beginning as early as 8 p.m. on Monday, November 8.

 

The left turn lane from westbound S.R. 46 to Wekiva River Road will be closed.

 

Intermittent lane closures and traffic pattern changes on Wekiva River Road will also occur.

 

These impacts are expected to last four weeks.

 

Remember to drive safely in the work zone and follow posted signage.

 

Please note construction schedules may change due to weather or other circumstances.

 

To learn more about the Wekiva Parkway project, please visit www.wekivaparkway.com or contact the project's community outreach team at 407-710-5610 or info@wekivaparkway.com.

Section 8: Ramp Closures Planned at I-4/S.R. 417/S.R. 46

November 5, 2021

Nightly ramp closures are scheduled Sunday, Nov. 7, through Friday, Nov. 12, at State Road (S.R.) 417 and Interstate 4 (I-4). Multiple ramps will close for bridge work.

 

Please see the following closures and detours:

  • Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road
  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to westbound/eastbound I-4 and International Parkway (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 7A: Closure of Lake Markham Road at S.R. 46 Planned

October 29, 2021

A continuous road closure and detour of Lake Markham Road at State Road (S.R.) 46 is planned to start as early as 8 p.m. on Sunday, October 31, as part of the Wekiva Parkway (S.R. 429) project. The closure will be in place for approximately two months.

Motorists should use Longwood Markham Road and Orange Boulevard as an alternate route.

Remember to drive safely in the work zone and follow posted signage.

Please note construction schedules may change due to weather or other circumstances. To learn more about the Wekiva Parkway project, please visit www.wekivaparkway.com or contact the project's community outreach team at 407-710-5610 or info@wekivaparkway.com.

 

Section 8: Ramp Closures Planned at I-4/S.R. 417/S.R. 46

October 29, 2021

Nightly ramp closures are scheduled Sunday, Oct. 31, through Friday, Nov. 5, at State Road (S.R.) 417 and Interstate 4 (I-4). Multiple ramps will close for bridge work.

 

Please see the following closures and detours:

·         Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road

·         International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road

·         Northbound S.R. 417 to westbound/eastbound I-4 and International Parkway (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46

·         Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com

 

Section 8: Ramp Closures Planned at I-4/S.R. 417/S.R. 46

October 22, 2021

Nightly ramp closures are scheduled Sunday, Oct. 24, through Friday, Oct. 29, at State Road (S.R.) 417 and Interstate 4 (I-4). Multiple ramps will close for bridge work.

 

Please see the following closures and detours:

  • Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road
  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to westbound/eastbound I-4 and International Parkway (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Additional nightly ramp closures planned for Sunday, Oct. 24, through Thursday, Oct. 28, are listed below:

  • Westbound I-4 ramp system to southbound S.R. 417 and C.R. 46A (7:30 p.m. – 6 a.m.): Use International Parkway to C.R. 46A
  • Eastbound and westbound S.R. 46 to westbound I-4 (7:30 p.m. – 6 a.m.): Use International Parkway

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 8: Ramp Closures Planned at I-4/S.R. 417/S.R. 46

October 15, 2021

Nightly ramp closures are scheduled Monday, Oct. 18, through Friday, Oct. 22, at State Road (S.R.) 417 and Interstate 4 (I-4). Multiple ramps will close for bridge work.

 

Please see the following closures and detours:

  • Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road
  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to westbound/eastbound I-4 and International Parkway (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Additional nightly ramp closures planned for Monday, Oct. 18, through Thursday, Oct. 21, are listed below:

  • Westbound I-4 ramp system to southbound S.R. 417 and C.R. 46A (8:30 p.m. – 6 a.m.): Use International Parkway to C.R. 46A
  • Eastbound and westbound S.R. 46 to westbound I-4 (8:30 p.m. – 6 a.m.): Use International Parkway

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

Section 8: Ramp Closures Planned at I-4/S.R. 417/S.R. 46

October 8, 2021

Nightly ramp closures are scheduled Sunday, Oct. 10, through Tuesday, Oct. 12, at State Road (S.R.) 417 and Interstate 4 (I-4). Multiple ramps will close for bridge work.

 

Please see the following closures and detours:

  • Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road
  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to westbound I-4 and International Parkway (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46

 

Additional nightly I-4 ramp closures and detours are listed below:

  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road
  • Westbound I-4 ramp system to southbound S.R. 417 and C.R. 46A (8:30 p.m. – 6 a.m.): Use International Parkway to C.R. 46A
  • Eastbound and westbound S.R. 46 to westbound I-4 (8:30 p.m. – 6 a.m.): Use International Parkway

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 8: Ramp Closures Planned at I-4/S.R. 417/S.R. 46

September 24, 2021

Nightly ramp closures are scheduled Sunday, Sept. 26, through Friday, Oct. 1, at State Road (S.R.) 417 and Interstate 4 (I-4). Multiple ramps will close for bridge work.

 

Please see the following closures and detours:

  • Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road
  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to eastbound I-4, westbound I-4 and International Parkway (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Nightly I-4 ramp closures are also planned Monday, Sept. 27, through Thursday, Sept. 30.

 

Closures and detours are listed below.

 

  • Eastbound and westbound S.R. 46 to westbound I-4 (8:30 p.m. – 6 a.m.): Use International Parkway
  • Westbound I-4 to southbound S.R. 417 and C.R. 46A (8:30 p.m. – 6 a.m.): Use International Parkway to C.R. 46A

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

Section 8: Ramp Closures and Detours Planned

September 17, 2021

Nightly ramp closures are scheduled Sunday, Sept. 19, through Friday, Sept. 24, at State Road (S.R.) 417 and Interstate 4 (I-4). Multiple ramps will close for bridge work.

 

Please see the following closures and detours:

  • Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road
  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to eastbound I-4, westbound I-4 and International Parkway (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Also, nighttime I-4 ramp closures are planned Thursday, Aug. 23. Closures and detours are listed below:

 

  • Eastbound and westbound S.R. 46 to westbound I-4 (8:30 p.m. – 6 a.m.): Use International Parkway
  • Westbound I-4 to southbound S.R. 417 and C.R. 46A (8:30 p.m. – 6 a.m.): Use International Parkway to C.R. 46A

 

Nightly roadway detours are also planned Sunday, Sept. 19, through Friday, Sept. 24, from 7 p.m. through 6 a.m., on Towne Center Boulevard between Rinehart Road and WP Ball Boulevard. For Towne Center Boulevard between S.R. 417 and WP Ball Boulevard, please use WP Ball Boulevard or Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 7A: Road Closure and Detour Planned on Longwood Markham Road at S.R. 46

September 15, 2021

A continuous road closure and detour of Longwood Markham Road at State Road (S.R.) 46 is planned to start as early as 8 p.m. on Wednesday, September 15, as part of the Wekiva Parkway (S.R. 429) project. The closure will be in place for approximately two months.

 

Motorists should use Lake Markham Road and Markham Road as an alternate route.

 

Remember to drive safely in the work zone and follow posted signage.

 

Please note construction schedules may change due to weather or other circumstances.

 

To learn more about the Wekiva Parkway project, please visit www.wekivaparkway.com or contact the project's community outreach team at 407-710-5610 or info@wekivaparkway.com.

Section 8: Ramp Closures Planned at I-4/S.R. 417/S.R. 46

September 10, 2021

Nightly ramp closures are scheduled Sunday, Sept. 12, through Friday, Sept. 17, at State Road (S.R.) 417 and Interstate 4 (I-4). The ramps from westbound I-4 to southbound S.R. 417, International Parkway to southbound S.R. 417, and northbound S.R. 417 to eastbound I-4, westbound I-4 and International Parkway will be closed for bridge work. The ramp system from eastbound I-4 to southbound S.R. 417 and S.R. 46 will also be closed.

 

Please use the following detours:

  • Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road
  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to eastbound I-4, westbound I-4 and International Parkway (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Nightly roadway detours are planned Sunday, Sept. 12, through Friday, Sept. 17, on Towne Center Boulevard between Rinehart Road and WP Ball Boulevard.

  • Towne Center Boulevard between S.R. 417 and WP Ball Boulevard (7 p.m. – 6 a.m.): Use WP Ball Boulevard or Rinehart Road

 

Nightly lane closures are scheduled from Sunday, Sept. 12, through Thursday, Sept. 16, on I-4 from S.R. 46 to C.R. 46A. Expect eastbound single lane closures 8:30 p.m. – 6 a.m. and double lane closures 10:30 p.m. – 6 a.m. Expect westbound single lane closures 7:30 p.m. – 6 a.m. and double lane closures 9:30 p.m. – 5:30 a.m.

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 7B: Traffic Shift Planned on S.R. 46

September 7, 2021

Section 7B of the Wekiva Parkway (State Road (S.R.) 429) project will move another step closer to its final configuration this week as traffic will be shifted to the newly constructed westbound lanes on S.R. 46.

 

The opening of the newly constructed westbound lanes, which are about 1.3 miles in length, will create improved access to neighborhoods and businesses on the north side of S.R. 46.

 

Traffic will be shifted to the new westbound S.R. 46 lanes from Wayside Drive/Oregon Street to Orange Boulevard as early as 8 p.m. on Tuesday, September 7.

 

Motorists are reminded to drive alert and follow posted signage.

 

Please note construction schedules may change due to weather or other circumstances.

 

To learn more about the Wekiva Parkway project, please visit www.wekivaparkway.com or contact the project's community outreach team at 407-710-5610 or info@wekivaparkway.com.

Section 8: Ramp Closures Planned at I-4/S.R. 417

September 7, 2021

Nightly ramp closures are scheduled Tuesday, Sept. 7, through Friday, Sept. 10, at State Road (S.R.) 417 and Interstate 4 (I-4). The ramps from westbound I-4 to southbound S.R. 417, International Parkway to southbound S.R. 417, and northbound S.R. 417 to eastbound I-4, westbound I-4 and International Parkway will be closed for bridge work. The ramp system from eastbound I-4 to southbound S.R. 417 and S.R. 46 will also be closed.

 

Please use the following detours:

  • Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road
  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Northbound S.R. 417 to westbound I-4 and International Parkway (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Nightly lane closures are scheduled from Tuesday, Sept. 7, through Friday, Sept. 10, on I-4 from S.R. 46 to C.R. 46A. Expect eastbound single lane closures 8:30 p.m. – 6 a.m. and double lane closures 10:30 p.m. – 6 a.m. Expect westbound single lane closures 7:30 p.m. – 6 a.m. and double lane closures 9:30 p.m. – 5:30 a.m.

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 8: Ramp Closures Planned at I-4/S.R. 417

August 28, 2021

Nightly ramp closures are scheduled Sunday, Aug. 29, through Thursday, Sept. 2, at State Road (S.R.) 417 and Interstate 4 (I-4). The ramps from westbound I-4 to southbound S.R. 417, International Parkway to southbound S.R. 417, and northbound S.R. 417 to westbound I-4 and International Parkway will be closed for bridge work. The ramp system from eastbound I-4 to southbound S.R. 417 and S.R. 46 will also be closed.

 

Please use the following detours:

  • Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road
  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway/westbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

 

Nightly roadway detours are planned Sunday, Aug. 29, through Monday, Aug. 30, on International Parkway between S.R. 417 and Wilson Road. In addition, nightly roadway detours are planned Monday, Aug. 30, through Thursday, Sept. 2, on Towne Center Boulevard between Rinehart Road and WP Ball Boulevard.

  • International Parkway between S.R. 417 and Wilson Road (7 p.m. – 6 a.m): Use Wilson Road or S.R. 417
  • Towne Center Boulevard between S.R. 417 and WP Ball Boulevard (7 p.m. – 6 a.m): Use WP Ball Boulevard or Rinehart Road

 

Nightly lane closures are scheduled from Sunday, Aug. 29, through Thursday, Sept. 2, on I-4 from S.R. 46 to C.R. 46A. Expect eastbound single lane closures 8:30 p.m. – 6 a.m. and double lane closures 10:30 p.m. – 6 a.m. Expect westbound single lane closures 7:30 p.m. – 6 a.m. and double lane closures 9:30 p.m. – 5:30 a.m.

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 7A: New Eastbound Lane to Open on S.R. 46 in Seminole County

August 25, 2021

Section 7A of the Wekiva Parkway (State Road (S.R.) 429) project will move another step closer to its final configuration this week as traffic will be shifted to the newly constructed eastbound lane on S.R. 46.

 

The opening of the newly constructed eastbound lane, which is about 1 mile in length, will create improved access to homes and businesses on the south side of S.R. 46.

Traffic will be shifted to the new eastbound S.R. 46 lane from east of Maureen Drive to North Orange Avenue as early as 8 p.m. on Wednesday, August 25. Additionally, a new roundabout at Glade View Drive will be partially opened to allow for local access. A temporary U-turn lane just east of North Orange Avenue will also be opened to further enhance local property access.

 

Motorists are reminded to drive alert and follow posted signage.

 

Please note construction schedules may change due to weather or other circumstances.

 

To learn more about the Wekiva Parkway project, please visit www.wekivaparkway.com or contact the project's community outreach team at 407-710-5610 or info@wekivaparkway.com.

Section 8: Ramp Closures Planned at I-4/S.R. 417/S.R.46

August 20, 2021

Nightly ramp closures are scheduled Sunday, Aug. 22, through Friday, Aug. 27, at State Road (S.R.) 417 and Interstate 4 (I-4). The ramps from westbound I-4 to southbound S.R. 417, International Parkway to southbound S.R. 417, and northbound S.R. 417 to eastbound/westbound I-4 and International Parkway will be closed for bridge work.  

 

Please use the following detours:

  • Westbound I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use I-4 to County Road (C.R.) 46A to Rinehart Road
  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Northbound S.R. 417 to International Parkway/westbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46

 

Also, nightly I-4 ramp closures are planned Sunday, Aug. 22, through Monday, Aug. 23 and Wednesday, Aug. 25, through Thursday, Aug. 26. The ramps from eastbound and westbound S.R. 46 to westbound I-4 will be closed.

 

  • Eastbound and westbound S.R. 46 to westbound I-4 (8:30 p.m. – 6 a.m.): Use International Parkway

 

In addition, nightly ramp system closures are planned from Sunday, Aug. 22, and Tuesday, Aug. 24, through Friday, Aug. 27. The ramp system from eastbound I-4 to southbound S.R. 417 and S.R. 46 will be closed, 8 p.m. – 6 a.m.

 

  • Use Rinehart Road as an alternative route

 

Nightly lane closures are scheduled from Sunday, Aug. 22, through Thursday, Aug. 26, on I-4 from S.R. 46 to C.R. 46A. Expect eastbound single lane closures 8:30 p.m. – 6 a.m. and double lane closures 10:30 p.m. – 6 a.m. Expect westbound single lane closures 7:30 p.m. – 6 a.m. and double lane closures 9:30 p.m. – 5:30 a.m. Also, nightly single lane closures are planned on International Parkway between Wilson Road and S.R. 417, 7 p.m. to 6 a.m.

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.