PROJECT NEWS

WEKIVA PARKWAY: Ramp closures planned at I-4/S.R. 417/C.R. 46A

October 27, 2023

Nighttime ramp and road closures are scheduled for Sunday, October 29, through Friday, November 3, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

  • International Parkway/I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway and westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A
  • C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road
  • Northbound Rinehart Road (7:30 p.m. – 6 a.m.): Use WP Ball Boulevard to Towne Center Boulevard 
  • Southbound Rinehart Boulevard (7:30 p.m. – 6 a.m.): Use Towne Center Boulevard to WP Ball Boulevard

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

 

WEKIVA PARKWAY: Section 8: Weekend Road Closure on Rinehart Road

October 27, 2023

A weekend road closure and detour are planned on Rinehart Road near State Road (S.R.) 417 from 7:30 p.m. Friday, October 27, to 6 a.m. Monday, October 30. The closure is necessary for bridge work. Please see the following detours:

 

  • Northbound Rinehart Road: Use Towne Center Boulevard to WP Ball Boulevard
  • Southbound Rinehart Road: Use WP Ball Boulevard to Towne Center Boulevard

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

 

Section 8: Ramp Closures Planned at I-4 / S.R. 417 / C.R. 46A / S.R.46

October 20, 2023

Nighttime ramp and road closures are scheduled for Sunday, October 22, through Friday, October 27, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

  • International Parkway/I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway and westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A
  • C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

 

Section 8: Nighttime Ramp and Road Closure at S.R. 417 and I-4

October 13, 2023

Nighttime ramp and road closures are scheduled for Sunday, October 15, through Wednesday, October 18, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

  • International Parkway/I-4 to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway and westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A
  • C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

A weekend road closure on Rinehart Road just north of S.R. 417 is scheduled for 7:30 p.m. Friday, October 20, through 6 a.m. Monday, October 23.

 

  • Northbound Rinehart Road at S.R 417: Use WP Ball Boulevard to Rinehart Road
  • Southbound Rinehart Boulevard at S.R. 417: Use WP Ball Boulevard to Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

 

 

 

Section 8: Nighttime Ramp and Road Closure at S.R. 417 and I-4

October 6, 2023

Nighttime ramp and road closures are scheduled for Sunday, October 8, through Thursday, October 12, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway and westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A
  • C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Nighttime closures on Towne Center Boulevard will occur on Sunday, October 8, and Monday, October 9.

 

  • Northbound Towne Center Boulevard at S.R 417 (7 p.m. – 6 a.m.): Use Rinehart Road to WP Ball Boulevard
  • Southbound Towne Center Boulevard at S.R. 417 (7 p.m. – 6 a.m.): Use WP Ball Boulevard to Rinehart Road

 

A weekend road closure on Rinehart Road just north of S.R. 417 is scheduled for 7:30 p.m. Friday, October 13, through 6 a.m. Monday, October 16.

 

  • Northbound Rinehart Road at S.R 417: Use WP Ball Boulevard to Rinehart Road
  • Southbound Rinehart Boulevard at S.R. 417: Use WP Ball Boulevard to Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

Section 8: Ramp and Closures Planned at I-4/S.R. 417/C.R. 46A

September 29, 2023

Nighttime ramp and road closures are scheduled for Sunday, October 1, through Thursday, October 5, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway and westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A
  • C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

 

Nighttime closures on Towne Center Boulevard and Rinehart Road at S.R. 417 will occur only as needed. These closures will not take place on the same night.

 

  • Northbound Towne Center Boulevard at S.R 417 (7 p.m. – 6 a.m.): Use Rinehart Road to WP Ball Boulevard
  • Southbound Towne Center Boulevard at S.R. 417 (7 p.m. – 6 a.m.): Use WP Ball Boulevard to Rinehart Road
  • Northbound Rinehart Road at S.R 417 (7:30 p.m. – 6 a.m.): Use WP Ball Boulevard to Rinehart Road
  • Southbound Rinehart Boulevard at S.R. 417 (7:30 p.m. – 6 a.m.): Use WP Ball Boulevard to Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

 

 

Section 8: Ramp closures planned at I-4/S.R. 417/C.R. 46A/S.R. 46

September 22, 2023

Nighttime ramp and road closures are scheduled for Sunday, September 24, through Thursday, September 28, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway and westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A
  • C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road
  • Northbound Towne Center Boulevard at S.R 417 (7 p.m. – 6 a.m.): Use Rinehart Road to WP Ball Boulevard
  • Southbound Towne Center Boulevard at S.R. 417 (7 p.m. – 6 a.m.): Use WP Ball Boulevard to Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

 

 

Section 8: Ramp closures planned at I-4/S.R. 417/C.R. 46A/S.R. 46

September 15, 2023

Nighttime ramp and road closures are scheduled for Sunday, September 17, through Thursday, September 21, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway and westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A
  • C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road
  • Northbound Towne Center Boulevard at S.R 417 (7 p.m. – 6 a.m.): Use Rinehart Road to WP Ball Boulevard
  • Westbound I-4 ramp to southbound S.R. 417 and C.R. 46A (7:30 p.m. – 6 a.m.) Use S.R. 46 to International Parkway
  • Southbound Towne Center Boulevard at S.R. 417 (7 p.m. – 6 a.m.): Use WP Ball Boulevard to Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

 

 

 

 

Section 8: Ramp closures planned at I-4/S.R. 417/C.R. 46A/S.R. 46

September 8, 2023

Nighttime ramp and road closures are scheduled for Sunday, September 10, through Thursday, September 14, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

·         International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road

·         Northbound S.R. 417 to International Parkway and westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A

·         C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46

·         Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road

·         Northbound Towne Center Boulevard at S.R 417 (7 p.m. – 6 a.m.): Use Rinehart Road to WP Ball Boulevard

·         Southbound Towne Center Boulevard at S.R. 417 (7 p.m. – 6 a.m.): Use WP Ball Boulevard to Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

 

 

Section 8: New NB S.R. 417 to EB I-4 Ramp Opening Planned

September 8, 2023

In the latest step toward finishing the Wekiva Parkway, a new ramp from northbound State Road 417 to eastbound Interstate 4 will open as soon as Monday, September 11. This longer ramp will provide greater sight distance for oncoming traffic and more opportunity to merge —enhancing motorists' safety.

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 8: Ramp and Road Closures at S.R. 417 and I-4

September 1, 2023

Nighttime ramp and road closures are scheduled for Tuesday, September 5, through Friday, September 8, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway and westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A
  • C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road
  • Northbound Towne Center Boulevard at S.R 417 (7 p.m. – 6 a.m.): Use Rinehart Road to WP Ball Boulevard
  • Southbound Towne Center Boulevard at S.R. 417 (7 p.m. – 6 a.m.): Use WP Ball Boulevard to Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 8: Ramp closures planned at I-4/S.R. 417/C.R. 46A/S.R. 46

August 25, 2023

Nighttime ramp and road closures are scheduled for Sunday, August 27, through Thursday, August 31, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway and westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A
  • C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road
  • Northbound Towne Center Boulevard at S.R 417 (7 p.m. – 6 a.m.): Use Rinehart Road to WP Ball Boulevard
  • Southbound Towne Center Boulevard at S.R. 417 (7 p.m. – 6 a.m.): Use WP Ball Boulevard to Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

 

 

Section 8: Ramp closures planned at I-4/S.R. 417/C.R. 46A/S.R. 46

August 18, 2023

Nighttime ramp and road closures are scheduled for Sunday, August 20, through Thursday, August 24, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A
  • C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road
  • Northbound Towne Center Boulevard at S.R 417 (7 p.m. – 6 a.m.): Use Rinehart Road to WP Ball Boulevard
  • Southbound Towne Center Boulevard at S.R. 417 (7 p.m. – 6 a.m.): Use WP Ball Boulevard to Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

 

 

Ramp closures planned at I-4/S.R. 417/C.R. 46A/S.R. 46

August 10, 2023

Nighttime ramp and road closures are scheduled for Sunday, August 13, through Thursday, August 17, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A
  • C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road
  • Northbound Towne Center Boulevard at S.R 417 (7 p.m. – 6 a.m.): Use Rinehart Road to WP Ball Boulevard
  • Southbound Towne Center Boulevard at S.R. 417 (7 p.m. – 6 a.m.): Use WP Ball Boulevard to Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

 

 

Section 6 -Large Sign Truss to Help Direct S.R. 46 West Traffic

August 9, 2023

As part of the Wekiva Parkway project, the Florida Department of Transportation today installed a large, overhead sign structure to help drivers continue on State Road 46 west when heading toward the Osprey Hammock Trail roundabout. The new signs indicate that those wishing to continue on S.R. 46 west to Sorrento or Mount Dora should stay to the left. Those wishing to get to River Oaks Circle or Wekiva Park Drive should take the bypass on the right.

 

A large turnaround area is also being completed at Wekiva Park Drive in case drivers errantly take the bypass.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.
 
To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 6: Traffic Stoppage Alert

August 9, 2023

As part of the Wekiva Parkway project, motorists should be alert for temporary traffic stoppages on State Road 46 westbound heading to the Osprey Hammock Trail roundabout on Wednesday, August 9. Crews at 10 a.m. will begin installing a large, overhead sign structure.

 

Electronic message boards will be posted and law enforcement will direct traffic. Please watch for stopped vehicles and be prepared for possible travel delays.

 

Access for emergency services and to nearby residences and businesses will be maintained.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.
 
To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 8: Ramp closures planned at I-4/S.R. 417/C.R. 46A/S.R. 46

August 4, 2023

Nighttime ramp and road closures are scheduled for Sunday, August 6, through Thursday, August 10, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A
  • C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road
  • Northbound Towne Center Boulevard at S.R 417 (7 p.m. – 6 a.m.): Use Rinehart Road to WP Ball Boulevard
  • Southbound Towne Center Boulevard at S.R. 417 (7 p.m. – 6 a.m.): Use WP Ball Boulevard to Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

 

 

Section 8: Ramp closures planned at I-4/S.R. 417/C.R. 46A/S.R. 46

July 28, 2023

Nighttime ramp and road closures are scheduled for Sunday, July 30, through Thursday, August 3, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A
  • C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road
  • Northbound Towne Center Boulevard at S.R 417 (7 p.m. – 6 a.m.): Use Rinehart Road to WP Ball Boulevard
  • Southbound Towne Center Boulevard at S.R. 417 (7 p.m. – 6 a.m.): Use WP Ball Boulevard to Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

 

 

 

Section 8: Weekend ramp closure planned at I-4/S.R. 417

July 28, 2023

A weekend ramp closure is scheduled for the westbound Interstate 4 (I-4) ramp to southbound State Road (S.R.) 417 from 7:30 p.m. Friday, July 28, to 6 a.m. Monday, July 31. The closure is necessary for bridge work.

 

  • Use County Road (C.R.) 46A to Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.

 

Section 8: Ramp closures planned at I-4/S.R. 417 starting July 24

July 21, 2023

Nighttime ramp and road closures are scheduled for Monday, July 24, through Thursday, July 27, at State Road (S.R.) 417 and Interstate 4 (I-4). The closures are necessary for bridge work.

 

Please see the following closures and detours:

 

  • International Parkway to southbound S.R. 417 (8 p.m. – 6 a.m.): Use S.R. 46 or C.R. 46A to Rinehart Road
  • Northbound S.R. 417 to International Parkway westbound/eastbound I-4 (8:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46 or C.R. 46A
  • C.R. 46A to eastbound I-4 (7:30 p.m. – 6 a.m.): Use Rinehart Road to S.R. 46
  • Eastbound I-4 ramp system to southbound S.R. 417 and S.R. 46 (8 p.m. – 6 a.m.): Use Rinehart Road
  • Northbound Towne Center Boulevard at S.R 417 (7 p.m. – 6 a.m.): Use Rinehart Road to WP Ball Boulevard
  • Southbound Towne Center Boulevard at S.R. 417 (7 p.m. – 6 a.m.): Use WP Ball Boulevard to Rinehart Road

 

Access to nearby residences and businesses will be maintained.

 

Electronic message boards will be posted.

 

For additional information, please contact the project’s community outreach team at 407-710-5610. You may also email the team at info@wekivaparkway.com.

 

To learn more about the Wekiva Parkway project, please visit wekivaparkway.com.